Parrott Drive Sanitary Sewer Project- Phase 1
Engineering Estimate: $1,450,000 | This project involves the replacement, rehabilitation and new installation of approximately 3,400 linear feet of 8-inch sanitary sewer pipes, within the public right-of-way and easement area. Pipe installation methods may include trenching or horizontal directional drilling (HDD) and pipe-bursting. The project also includes manhole removal/ replacement, new manhole installation and safely removing and disposing of asbestos concrete pipes (ACP).
Addendum No. 1
(click to expand/collapse)

Name | Size | ||
Addandum 1 | 171.0 KB |
Q&A / QC
(click to expand/collapse)

Name | Size | ||
Meeting-Notes | 193.8 KB |