Parrott Drive Sanitary Sewer Project- Phase 1

Engineering Estimate: $1,450,000 | This project involves the replacement, rehabilitation and new installation of approximately 3,400 linear feet of 8-inch sanitary sewer pipes, within the public right-of-way and easement area. Pipe installation methods may include trenching or horizontal directional drilling (HDD) and pipe-bursting. The project also includes manhole removal/ replacement, new manhole installation and safely removing and disposing of asbestos concrete pipes (ACP).